September 2, 2024
September 2, 2024
September 2, 2024
August 16, 2024
August 16, 2024
August 16, 2024
February 4, 2022
On January 20, we held our Topping Out Ceremony to mark the completion of the structural phase of the project, and now we are redirecting our focus on the MEP and interior works.
January 19, 2022
Rose Apple Square was excited to be one of the sponsors for the 26th Annual Angkor Wat International Half Marathon. Due to COVID restrictions, the event was pushed back from its traditional date at the beginning of December to Sunday, January 2nd.
January 3, 2022
December was a BIG month for the construction side. On December 30 we poured and topped off level 7 of the final section. This means that the largest structural works are now complete, and we’ll be directing our focus on all the other areas.